Timeframe
|
Key Milestones |
Timeframe |
|
Member enablement and engagement activities commence and proceed through the life of the project |
Late October 2011 |
|
Senior staff of all member organizations briefed on KAREN2 |
By December 2011 |
|
Draft architecture published for community comment. |
November 2011 |
|
Procurement process commenced |
March/April 2012 |
|
Procurement process completed including in-premises evaluation of key technologies and preferred vendor established |
September 2012 |
|
Selection of new Transport Service Manager (to manage transport layer) |
November 2012 |
|
Pilot Project Initiated (if required) |
February 2013 |
|
1st Phase Implementation |
June-November 2013 |
|
Transition to KAREN2 |
Early December 2013 |
|
Pacific Fibre International connectivity on-stream |
Mid 2014 |
|
Subsequent Phases if required (depending on the overall project cost some secondary elements of KAREN2 may be implemented in a later phase). |
Post February 2014 |